You might have assigned a task to a user who is already overloaded with work. In such cases, you may need to split the assignment.
You can divide the assigned hours among multiple users by following the instructions below. 


To split a task assignment:

  1. Go to the Assignments tab in Resource Management.

  2. Search for the task assignment that you want to split.

  3. Hover over the task assignment name, right-click it, and select the Split Assignment option.

  1. In the next window, you can view the total task hours and the hours assigned to the users.
  2. Select users from the user list and enter the hours for their task assignments, and click the Apply button.


Note:

  • If you need to edit the assigned hours for a user, you can do so from the Edit Task Assignment page. The hours assigned to users cannot be edited from this window.
  • You can also delete an assignment using the Delete icon.