To update the details of an existing task (To Do), follow the steps below:


  1. Go to Project Management V2 and select the relevant Project.

  2. Click on the To Dos list and locate the Task you want to edit.

  3. Click the Pencil icon next to the Task name to open the edit view.

  4. Make the necessary changes, such as:

    • Task Name

    • Start Date/time and End Date/time

    • Hours Assigned

    • Description

  5. Once you’ve made the updates, click the Update Task button to save your changes.