There is no limitation on the number of users you can assign tasks to. You can assign a task to any number of users who report to you. 


  • To assign the tasks
    1. Select the project from the Projects list and click the + button.
    2. In the New Task pop-up, enter the Task Assignment Title, Start Date, End Date, Assigned Hours, and any relevant Notes.
    3. Go to the Resources tab, search for the user in the User Assigned field, enter the Assigned Hours, and click the Add button.
    4. Return to the General tab and click the Done button.
  • The user's initials will now appear next to the task name in the Gantt Chart, indicating that the task has been assigned to them.

  • Click here to know more about assigning tasks to the users